A raised access floor is a system, not a tile. Panel, stringer, pedestal and finish decide whether the floor stays level after five years of loaded cabinets and repeated access.
Panel construction
Steel-encapsulated cementitious panels at 600 x 600 x 35 mm are the standard for data rooms and offices; solid steel panels are used where point loads are high. For antistatic applications the finish is HPL or conductive vinyl with a surface resistance in the 10^6-10^9 ohm range, bonded to the panel core rather than laid loose.
Load class
State concentrated load and ultimate load – for example 1200 kgf/m2 uniformly distributed with a 300 kg point load at the panel centre. Rooms with UPS and battery cabinets usually need the next class up, and pedestal spacing must match.
Support height and stringers
Finished floor height follows the cable and air path underneath: 600 mm is common for data rooms, 300-500 mm for offices. Stringers connect pedestals and reduce panel rocking; bolted stringers are preferred where the floor is accessed often.
Ventilation
Perforated panels are specified by open area – 35 percent for cold aisle delivery, 17-25 percent for general rooms. Confirm how many perforated panels sit in the layout and that airflow matches the cooling capacity.
Finishing and edges
Check edge sealing, corner locking and tolerance between panels. A floor that reads well on a drawing can still rock when levelling is not specified and installation is not supervised.
Send the room size, cabinet layout and required finished height for a panel schedule and pedestal count. WhatsApp · zhangxt@sykj-sh.com